Construction Update - March 6, 2024
File Construction completed concrete work and site grading. Next step is to install the emergency generator, propane tank and pumps. Alderman Electric will be installing the controls soon. The jib crane will be installed next week after the concrete pad has had time to cure. PNM has the easement drawings and will hopefully install the new electrical service soon.

Interior of wet well

Valve basin

View of wet well in foreground and valve basin in background

Wet Well and Valve Basin

Stainless Steel high pressure lines

Trenching in discharge line

Lift Station Basket

Shop Towels and Wipes from Basket

Trenching in water lines

Original 2 inch water line

Connectors between basins installed

Connection to the new lift station from the Townsite influent line

Sanitizing and pressure testing the new 2 inch water line to the new lift station

Backfilling and compacting soil around the two basins. All connections to the input and discharge have been completed today.

Propane and generator pads

Jib crane foundation prep

Another view of propane and generator pads

Jib crane concrete form

Jib crane onsite

Basket in Wet Well

Tie-in to new lift station

Concrete base for new manhole

Generator pad and propane tank pad

Preparing to enter the elevated tank to clean

The orange hose sucks out the sediment on the bottom of the tank

D&R Tank inspector measuring the thickness of the steel

Alderman Electric working on electrical panels

Operator's panel at wet well

Rebar in jib crane foundation

Final grading of the lift station pad

Final grading of the lift station pad

Flowmeter vault installed today